19/11/2007
II. Repair of Infrastructure     
  Baseline Value Progress To Date  Progress Indicator Remarks
 
1) Bridges 91bridges destroyed  74 (Permanent) Bridges Completed 81 % completed 1 bridge in the final process
       
2) Telecommunications 58 damaged/destroyed telephone exchanges 58 repaired  100 % repaired 
5 damaged generating stations 4 repaired  80 % repaired Service provided through replacements, awaiting arrival of new equipment'
103 damaged public phone centers  70 rehabilitated  68 % rehabilitated  waiting completion of repairs in destructed networks
Main Networks  100 % rehabilitated 
Secondary Networks  Most Remains totally destroyed networks of Bint Jbeil & Beirut Southern Suburbs
10 Transmission Equipment 8 restored  80 % restored  Service provided through replacements, awaiting arrival of new equipment'
34 damaged Fiber Optic Cables 34 repaired 100 % repaired
6 damaged Microwave units 6 repaired  100 % repaired
2 damaged Wave Guides 2 repaired 100 % repaired
       
3) Water  58 damaged Reservoirs 55 repaired 95 % repaired  3 funded UNICEF being contracted
20 damaged Pumps 20 repaired 100 % repaired
2 damaged Artesian Wells 2 rehabilitated 100 % rehabilitated
1514 damaged points on Network/Pipeline 1514 rehabilitated 100 % rehabilitated
       
4) Electricity 5 damaged fuel oil tanks in Jieh thermal station 0 repaired  15 % rehabilitated  Replacement: Floating Boat for 4 months, Signed agreement with Petrojet-Egypt
transmission lines 100 % rehabilitated transmission lines 
distribution lines 95 % rehabilitated distribution lines
       
4) Schools 929 schools totally or partially destroyed or damaged  798 rehabilitated  86 % rehabilitated Totally destructed schools still under construction
       
5) Airports 5 damaged runways 5 repaired  100 % repaired 2 RHIAB, 1 Qulaiat, 1 Riyak
3 damaged fuel tanks (RHIA) 2 repaired 75 % repaired