II. Repair of Infrastructure     
  Baseline Value Progress To Date  Progress Indicator Remarks
 
1) Bridges 91bridges destroyed  64 (Permanent) Bridges Completed 70 % completed 8 bridges in the final process
       
2) Telecommunications 58 damaged/destroyed telephone exchanges 58 repaired  100 % repaired 
5 damaged generating stations 4 repaired  80 % repaired Service provided through replacements, awaiting arrival of new equipment'
103 damaged public phone centers  70 rehabilitated  68 % rehabilitated  waiting completion of repairs in destructed networks & arrival of new ordered equipment
Main Networks  100 % rehabilitated 
Secondary Networks  Most Remains totally destroyed networks of Bint Jbeil & Beirut Southern Suburbs
10 Transmission Equipment 8 restored  80% restored 
Service provided through replacements, awaiting arrival of new equipment'
34 damaged Fiber Optic Cables 34 repaired 100 % repaired
6 damaged Microwave units 6 repaired  100% repaired
2 damaged Wave Guides 2 repaired 100% repaired
       
3) Water  58 damaged Reservoirs 51 repaired 88% repaired 3 will be finalized in August 2007, Rest waiting UNICEF approval for contracting
20 damaged Pumps 20 repaired 100% repaired
2 damaged Artesian Wells 2 rehabilitated 100% rehabilitated
1514 damaged points on Network/Pipeline 1514 rehabilitated 100% rehabilitated
       
4) Electricity 5 damaged fuel oil tanks in Jieh thermal station 0 rehabilitated  15% rehabilitated  Replacement: Floating Boat, Signed agreement with Petrojet-Egypt
transmission lines 100% rehabilitated transmission lines 
distribution lines 95% rehabilitated distribution lines
       
4) Schools 862 schools totally or partially destroyed or damaged  791 rehabilitated  92% rehabilitated
       
5) Airports 5 damaged runways 5 repaired  100 % repaired 2 RHIAB, 1 Qulaiat, 1 Riyak
3 damaged fuel tanks (RHIA) 2 repaired 67 % repaired